Georgia Power’s Vogtle Unit 3 Achieves Initial Energization

View All News

May 7, 2019

News

The following is a Georgia Power news release:


Georgia Power announced today that plant equipment for Vogtle Unit 3 is now energized, or permanently powered, which is needed to perform all subsequent testing for the unit. With plant equipment previously running on temporary construction power, the completion of initial energization represents a significant milestone in the Vogtle expansion as the project moves from construction toward system operations.

Significant progress continues at the site, with the project now approximately 77 percent complete. With more than 7,000 workers currently onsite and more than 800 permanent jobs available once the units begin operating, Vogtle 3 & 4 is currently the largest jobs-producing construction project in the state of Georgia.